CANORECO Balita

MGA MAINTENANCE WORK NA NAGAWA NOONG MARCH 13, 2021 SCHEDULED POWER SERVICE INTERRUPTIONS

Sa Power Service Interruption na ini-schedule ng Area 1 Office (A1O) noong March 13, 2021 (Sabado) mula 6:00 ng umaga hanggang 12:00 ng tanghali sa Brgy. Borabod, Awitan at Bagasbas, at Sitio Mandulungan sa Brgy. Gubat sa bayan ng Daet; at San Nicolas sa bayan ng TALISAY, nagawa ang sumusunod na maintenance work:
– Relocation of poles (DPWH road clearing) at tapping of backbone lines sa Brgy. Borabod, Daet.

Sa Power Service Interruption na ini-schedule rin ng Area 1 Office sa parehong petsa mula 6:00 ng umaga hanggang 2:00 ng hapon sa buong bayan ng BASUD, Coastal barangays ng MERCEDES at South barangays ng SAN LORENZO RUIZ, nagawa ang sumusunod na maintenance work:
– Right Of Way (ROW) clearing of lines mula Brgy. San Felipe hanggang Caayunan, Basud;
– Relocation of poles (DPWH road clearing) at re-tensioning of wires sa Brgy. San Felipe, Basud;
– Installation of lines sa Colasi Mini Hydro Electric Power Plant; at
– Installation of secondary lines sa Mangcamagong Rd., Basud.

Ang mga maintenance activity na ito ay isinasagawa para sa kaayusan ng mga linya ng kuryente at para sa mas maayos na serbisyong hatid ng CANORECO.

Para sa karagdagang impormasyon, makipag-ugnayan sa mga sumusunod na cellphone nos. 09081865100 at 09190952707, at landline no. 054-5713796 (Area 1); 09951305414 (Labo); 09150076861 (Bagong Silang); 09270318517 (Sta. Elena); 09675945749 (Capalonga); 09106346328 (Batobalani); 09079151163 (Paracale); at 09632251930 (Jose Panganiban).