Maintenance Activities

MGA MAINTENANCE WORK NA NAGAWA NOONG SEPTEMBER 12, 2020 SCHEDULED POWER SERVICE INTERRUPTIONS

Sa Power Service Interruption na ini-schedule ng Area 1 Office (A1O) noong September 12, 2020 (Sabado) mula 7:00 ng umaga hanggang 9:00 ng umaga sa buong bayan ng Talisay; Vinzons; Labo maliban sa Southroad barangays; at Brgy. Dancalan, Awitan, Tabas, Labnig, Bakal at Mangkasay, Paracale, nagawa ang mga sumusunod na maintenance work:
– Correction of hotspot and re-tapping of twelve (12) connections in Brgy. Calintaan, Poblacion, Sto. Niño, Talisay; and
– Replacement of one (1) insulator in Brgy. Sto. Niño, Talisay.

Sa Power Service Interruption naman na ini-schedule din sa parehong araw mula 7:00 ng umaga hanggang 12:00 ng tanghali sa buong bayan ng San Vicente; Brgy. Alawihao, Dogongan at bahagi ng Lag-on, Daet; at bahagi ng Brgy. Itomang, Binanuaan at Cahabaan, Talisay, nagawa ang mga sumusunod na maintenance work:
– Removal of ten (10) old primary line assemblies along Brgy. Binanuaan, Talisay;
– Right of Way (ROW) clearing of lines in Brgy. Calintaan and Itomang, Talisay, and in Alawihao and Lag-on, Daet; and
– Pull out of nine (9) old poles and secondary hotlines along Diversion Rd., Brgy. Lag-on, Daet.

Para sa karagdagang impormasyon, makipag-ugnayan sa Area 1 Office (A10) sa cellphone no. 09081865100 at landline no. 054-5713796.